Current BMU Projects

Townline Road Water Main Replacement

Bryan Municipal Utilities’ Townline Road Water Main Replacement Project is scheduled to begin Friday, June 21, at the intersection of High Street and Townline Road.

The Project includes installation of approximately 4,400 feet of 12-inch water main, seven fire hydrants and 30 water service lines within the public right-of-way on Townline Road between High and Center streets.

Project contractor Underground Utilities, Inc. of Monroeville, Ohio, will work in and along Townline Road; as a result the road will be closed to through traffic during construction. However, Underground Utilities will work to keep area residences and emergency services accessible throughout the project. Motorists are encouraged to seek alternate routes during Project work hours.

Work will be performed from approximately 7:00 a.m. to 5:00 p.m. Monday through Thursday with Friday serving as a make-up day as needed. Estimated project completion date is September 23, 2019, weather permitting.

Townline Road will be open for those attending Bryan’s Day in the Park event and fireworks at the Bryan Recreation Park on Saturday, June 22.

The Townline Road Water Main Replacement Project replaces an aging six-inch water main, improving water service reliability and increasing firefighting capability in the Project area. The Project also eliminates a hydraulic bottleneck in the 12-inch water transmission loop around the City Bryan.

Additional information is available at www.cityofbryan.net/projects or by following Bryan Municipal Utilities on Facebook.

Stuart Martin:
–Office: 419-633-6144
–Work Cell: 419-519-0516

Current Project Location and Road Closure:

UPDATES:

6/5/19: Crews are expected to begin moving equipment and materials into the area Monday, June 17th, with a start date of Monday, June 24th.  **Weather Permitting.

6/24/19: Townline Rd is closed between West High Street and Rays Drive.

6/26/19 Townline is closed between High St and Oakwood. Oakwood is open for a detour route.  Ray’s Drive is open up to Townline.

7/31/19 – Crews have completed installing the new 12″ water main.  Work is beginning on the High St. end of Twonline Rd to connect customers to the new main.

Fairview Drive Directional Boring Project

Bryan Municipal Utilities plans to replace the direct-buried underground electric lines that currently serve your property and/or residence. The project consists of installing (boring) new conduit and electric wires underground between the transformers & vaults/pedestals within the utility easement(s) located in the rear or side(s) of your property.  This capital improvement project will replace aging wires (40+ years old), improving electric service reliability in the area.

The project limits begin – relating to the Project Map Overview sheet provided with this letter – at the rear of 321 Lawndale Drive, commencing south to the rear of 324 Fairview Drive, then east to the rear of 550 Lawndale Drive & 1210 Bellaire Avenue.  It then continues starting behind 321 Fairview Drive then east until stopping behind 510 Lawndale Drive.  Finishing off the project it begins at the rear of 502 Fairview Drive and continues south to the north side of 420 Fairview Drive.  The project is divided in to three phases known as:  Construction, Installation, and Restoration.  Each phase may require the contractor to be on your property (within the utility easements) multiple times conducting the necessary work in order to achieve full completion of the project.  The exact order of process and location in which the contractor starts and completes their work is subject to change at any time during the project.

S & S Directional Boring, LTD. will be the contractor for this project.  At various times throughout the project the contractor may need to gain access through the rear or side(s) of your property from the roadway with equipment & materials.  We apologize for any inconvenience or disturbance this may cause.  We want to make you aware that all restoration to any part of your property affected by this project will be addressed by the contractor and/or BMU at the end of the project.  This project is estimated to begin its construction phase sometime near the date of July 1st, 2019.

419.633.6143
Britton Poynter
Engineering Assistant
Bryan Municipal Utilities

UPDATES:

Helpful Information for Homeowners